Skip to main content

Table 4 Summary and comparison of the BAU scenario with other scenarios in Section 3.5

From: Planning of Food-Energy-Water-Waste (FEW2) nexus for sustainable development

 

CAPEX (million AUD)

OPEX (million AUD per annum)

Cost PV (million AUD)a

Compared to BAU

PV of avoided costs from BAU (million AUD)

PV of equivalent revenue of generated energy (million AUD)

BAU

228

38

370

–

–

Biosolids

150

6.6

279

33.2 (management cost)

9.22

MSW

136

5.6

98.3

28.3 (landfill levy)

89.8

Agricultural & other organic Waste

258

10.7

173

44.4 (landfill or gate fee)

146

  1. aCAPEX and OPEX over 20 years are included in cost PV